September’s addition and remodeling progress…

It’s been a very productive month, about which we couldn’t be more pleased and excited. If you need a refresher of where we last left our heroes, you can skim through the pictures in the September 5 update.

People kept asking us how many square feet we were adding on, and we finally got tired of answering, “We don’t know,” so we contacted the architects who informed us that we’re going from 1000 square feet to 1,500 square feet.
Hooray!

The executive summary of this month’s progress is:

  • Framing of new areas (porch, master bathroom, master bedroom closet, storage areas) completed
  • Water heater moved
  • Existing kitchen demolished
  • New plumbing roughed in
  • New electrical wiring roughed in

September 2, 2016 — Screened-in porch framing
Porch framing

September 4, 2016 — Kitchen, master bathroom, and master bedroom framing
Kitchen, master bathroom, master bedroom framing

September 6, 2016 — Porch roof framing
Porch framing

September 8, 2016 — Porch roof
Porch roofing

September 15, 2016 — Skylights / solar tubes arrive
Skylights and solar tubes

September 16, 2016 — Kitchen and master bathroom skylights
Kitchen and master bathroom skylights

September 16, 2016 — New roof over back storage shed, porch, and master bedroom
(as seen from our neighbor’s yard)
New roof and side view from neighboring yard

September 17, 2016 — Fridge and microwave moved into the living room
in advance of the kitchen demolition

Fridge and microwave now in living room

September 17, 2016 — Bob removed cabinets, counters, and the stove!
Stove, cupboards, and counters gone

September 17, 2016 — Bob also removed the island that was in the kitchen!
Kitchen island gone

September 19, 2016 — Kitchen back wall, sink, window, and cabinets demolished
Gutted kitchen

September 19, 2016 — View from old kitchen opening into
new galley kitchen area replacing it

Kitchen sink, window, and wall gone

September 19, 2016 — Diana and Rollo at work
Dianna and Rolo working

September 26, 2016 — View from existing TV room into new master suite
(hallway in middle, closet to the right, master bathroom to the left, bedroom in the back)
View into new master suite

September 26, 2016 — New storage area in the hallway
that leads to existing bathroom

New hallway storage area

September 29, 2016 — Back of house (master bedroom, porch, and shed) walled and roofed
Back view of master suite, porch, and storage shed

September 30, 2016 — Exhaust fan and canned lighting in new master bathroom
Canned lighting

September 30, 2016 — Electrical work roughed in
Electrical wiring rough-in

September 30, 2016 — Plumbing work roughed in
Washer and dryer plumbing

September 30, 2016 — New air intake facing the master suite hallway
Air intake

Coming soon: Insulation, sheetrock, floors, and cabinets…