We’re finally able to see a little bit of light at the end of the tunnel, and we’re pretty sure it’s not a train coming back at us. We’re in the stage now where everything is very exciting.
Our last update for the October and November progress was quite recent, so you probably don’t need a refresher.
And, if you’re interested, you can see all of my blog entries about the project, which started back in June.
The executive summary of the progress for these first 2 weeks of December is:
- Shower walls and tile
- Appliances “ready to go”
- Deck poles and flooring
- Cabinets
- Mud sink
- Countertops
- Wet bar
- Porch and deck railings
waiting in the garage (amidst a good portion of the rest of our house
that’s been “stored away” during this renovation and addition)
of our new galley kitchen
with adjustable shelves
the sink and faucet are installed. Bar fridge coming, too.)
Coming soon: Back splashes, floors, appliances, and interior walls painting…